Camberley May Update

Work is progressing on the design & build care home project in Camberley, Surrey.

As part of the planning permission granted, we had to demolish the rear of the building and keep the front facade. Once the rear was complete and the front facade was unveiled it quickly became apparent the poor condition of the front. With dry rot, poor construction and general bad condition, we have returned to planning to request the removal of the front facade. Currently, we are awaiting their decision.

In the meantime to minimise delays to the project we have working on the rear of the building. Setting foundations and starting on the construction of walls.

This unforeseen circumstance has put us a little behind, but we are confident we will be able to make up the time, to meet our deadline for completion December 2018.

Read more about the new care home in Camberley we are building in our Work in Progress section